How to Measure Changeover Time with Machine Data
DBR77 Team · Published
To measure changeover time with machine data, record four time stamps for every changeover: the last good part of the old order, the moment the machine stops, the first cycle of the new order and the first good part at normal rate. Changeover time runs from the last good part to the first good part at rate, so it includes the run-up that a stopwatch from stop to start misses. The machine supplies the stop and the cycle counts, and one input from the operator or the order change says that the stop is a changeover and which product comes next. Collected for every changeover, these records give the median time and the spread per product pair, shift and crew, which is what a SMED program and OEE need.
Most plants know their changeover time from one video study or from times typed in at the end of the shift. In a NIST MEP success story, a Michigan machining, grinding and assembly company videotaped a changeover that took 8 hours and 20 minutes and then cut the time by 70%. A study like that takes one changeover apart task by task. It cannot show how the time varies over the hundreds of changeovers that follow, which in many plants are simply not recorded: researchers working with CNC machines note that "the changeover interval is not documented" (Engelmann et al.).

What changeover time is, and where it starts and ends
Changeover time is the time from the last good part of one run to the first good part of the next run at normal rate. The Lean Enterprise Institute describes a changeover as switching a machine or line from one product to another "by changing parts, dies, molds, fixtures, etc." and adds that it is "also called a setup". LEI measures it as "the time elapsed between the last piece in the run just completed and the first good piece from the process after the changeover."
Christoph Roser adds the speed condition: a changeover runs "from the last part at full quality and production speed" to "the first new part at full quality and production speed" (AllAboutLean). Researchers at the University of Bath describe three phases, "run-down, set-up and run-up" (Mileham et al.). A stopwatch started when the machine stops and stopped when it runs again measures only the middle one.
| Phase | Starts with | Ends with | What happens |
|---|---|---|---|
| Run-down | Last good part of the old order | Machine stops | Last parts, emptying, the machine slows down |
| Set-up (internal) | Machine stops | First cycle of the new order | Dies, tools, fixtures and settings are changed |
| Run-up | First cycle of the new order | First good part at rate | Adjustment, first-piece approval, scrap, slow cycles |
Write the rule down before you collect a single record. One page is enough, and it should answer three questions:
- What counts as good. Usually the first part that passes first-piece approval under your quality plan.
- What counts as "at rate". We suggest a fixed number of consecutive cycles at or near the standard cycle time, set per machine. No standard gives a number, so pick one and keep it.
- What happens to breaks and breakdowns inside a changeover. Count them in or split them out; either works if every shift applies the same choice.


The signals and inputs that mark each boundary
Each of the four time stamps needs a source you can trust, and the source depends on what the machine can report. A raw stop signal looks the same for a changeover, a breakdown or a wait for material, so at least one boundary needs a person or an order system to say what the stop is.
| Moment | What marks it | Machine with a controller | Machine without a PLC |
|---|---|---|---|
| 1. Last good part of the old order | Last counted part that is not scrapped | Part count from the PLC or a Modbus meter | Count from a cycle sensor, stack light or motor current, plus a scrap entry |
| 2. Machine stops for the changeover | Stop time plus the reason "changeover" | Stop from the machine, reason from the operator; a "Setup" mode on machines that implement OPC UA for Machinery | Operator sets "changeover" at the machine |
| 3. First cycle of the new order | Cycle count starts again | Cycle count; order change in MES or ERP | Cycle sensor; operator sets "running" |
| 4. First good part at rate | Cycles at standard rate with no scrap | Cycle time from the counts, scrap reported against the order | Counts plus the operator's scrap entry |
Newer machines can give a direct signal. OPC UA for Machinery defines a "Setup" operation mode, used "with the intention to carry out setup, preparation or postprocessing" activities; on machines that implement it, the mode change marks the internal setup. PackML packaging machines have unit modes such as Producing, Maintenance and Manual, and the specification names others, such as Clean and Calibration, as examples. If your machine has no changeover mode, the changeover has to come from the operator or from the order change.
The ISO 22400 annex of OPC UA for Machinery ties setup time to an order: its condition is "system state is order registered". Link every changeover record to its order too, or you will not know which product pair it was. Our article on machine data and context sets out a state model in which changeover is its own state, started by the operator or by the order change.
On older machines, a stack light tap, motor current or a cycle sensor gives the stop and the counts (see connecting old machines without a PLC). Researchers have gone further and told changeover apart from production on a CNC milling machine from sensor data, with "an overall accuracy of 92.8%" in a research setting (Engelmann et al.). For a first project, one operator input at the start and end of the changeover is simpler and easier to check.
See how a changeover shows up in the data
Bring one machine with frequent changeovers and tell us whether it has a PLC. In the call we show how the changeover state, stops and counts look in DBR77 IIoT, and what you would need to see product pairs.
How to measure changeover time on one machine
Set up the measurement on one machine and check it for two weeks before you add more machines.
- Pick the machine. Choose the one where changeover minutes cost most: the most changeovers per week, or the longest ones. If that machine limits the whole line, every minute there is lost line output.
- Write the start-and-end rule. Use the three questions from the first section and agree the answers with production, quality and the crews of every shift.
- Connect the stop and cycle signals. PLC or Modbus where there is a controller; a cycle sensor, stack light or motor current where there is not.
- Give the operator a simple input at the machine. Setting it to "changeover" marks the start, and setting it back to "running" marks the end. Keep the reason list short and add a sub-reason, such as "waiting for tool", only when it leads to a different action.
- Attach the order or product to each changeover. Take it from the order change in MES or ERP, or from the work order shown at the machine. What data to collect from machines covers this kind of context.
- Check for two weeks, then drop the stopwatch. Compare one observed changeover per shift with its record. When they disagree, fix the rule or the habit instead of editing the record.

DBR77 IIoT Status Deck in the animation on the product page: the ring set to changeover, with the reason and the stop on the shift timeline (illustrative animation, DBR77).
Operator input is only as good as the habit behind it, and the machine's own signals keep it honest. A machine in "changeover" state that is still counting cycles, or a stop with no reason right after an order change, is a record to check the same day.
How to split internal and external setup with data
Shigeo Shingo's SMED method separates internal setup, work "which can be done only when a machine is stopped (such as inserting a new die)", from external work "that can be performed while the machine is running", and then moves as much internal work as possible to external. Its target is "reducing changeover times to a single digit, or less than 10 minutes" (LEI, SMED).
Machine data measures internal time (the stop in changeover state) and run-up (cycles below rate or with scrap). External work happens while the machine runs, before or after the stop, so the data cannot time it. Time the external tasks once in an observation or video study, write them into a checklist, and from then on use the data to see whether that work has moved back inside the stop.
Signs in the data that this has happened:
- Gaps inside the changeover marked "waiting for tool", "waiting for material" or "waiting for approval".
- Internal time that grows on shifts with fewer people.
- Run-up that grows after a faster setup. The Bath team notes that "doing a set-up fast can often result in a disproportionate increase in run-up."
- A wide spread on one product pair while the other pairs stay stable.
Reading the data by product pair, shift and crew
Report changeover time per product pair as a median and a range, next to the number of changeovers, because the cost is how often multiplied by how long. An average of a few records hides the long changeovers that matter, and a pair with only a few records is provisional.
The two tables below are a modelled base case: one press, three products (A, B and C), four weeks, 30 changeovers.
| Product pair | Changeovers | Median (min) | Range (min) |
|---|---|---|---|
| A to B | 6 | 34 | 28 to 45 |
| A to C | 4 | 71 | 58 to 96 |
| B to A | 7 | 31 | 26 to 40 |
| B to C | 5 | 52 | 44 to 70 |
| C to A | 4 | 63 | 50 to 88 |
| C to B | 4 | 47 | 39 to 61 |
Changeovers into or out of product C take about twice as long as those between A and B. The pairs are not symmetric: B to C takes 52 minutes, C to B takes 47. A to C has the widest range, so either no standard exists for that pair or it is not followed. For a planner, this table is the sequence data that production plans need: in this example the sequence A, B, C costs 86 minutes of changeover and A, C, B costs 118.
The same press by shift, with typical minutes per changeover (total = internal + run-up; run-down took under a minute and is left out):
| Shift | Changeovers | Internal (stopped) | Run-up | Total |
|---|---|---|---|---|
| Shift 1 | 11 | 31 | 9 | 40 |
| Shift 2 | 10 | 33 | 15 | 48 |
| Shift 3 | 9 | 35 | 24 | 59 |
Internal time is close across the shifts, and run-up differs most. The gap is in adjustment and first-piece approval, which points to a missing standard for that step rather than a slow crew. Use crew comparisons to find the best practice and write it down. If people expect the numbers to be used for blame, the habit of marking changeovers breaks first (see when operators don't trust the data yet). A changeover still running at the end of a shift should go to the next shift with its elapsed time, as part of the shift handover.
Using the numbers in a SMED program and in OEE
With the records, a SMED program becomes a loop you can check after every changeover:
- Take the baseline per product pair from four weeks of records.
- Video one representative changeover of the worst pair, as the Michigan team did in the NIST MEP story.
- Separate internal and external work, move what you can to external, and standardize the rest.
- Check every changeover after the event. Watch run-up as closely as internal time, because a faster setup can make run-up longer.
The data shows which changeover costs most. A bad changeover standard still has to be rewritten by people on the floor.
In OEE, one changeover touches all three factors. The stopped part is an availability loss: the "Setup and Adjustments" loss on OEE.com covers "setup, changeovers, major adjustments, and tooling adjustments". Scrap during run-up is a quality loss, "Reduced Yield", which "is most commonly tracked after changeovers". Slow cycles during run-up lower performance. In the ISO 22400 time model as OPC UA for Machine Tools applies it, "Availability = APT / PBT" (actual production time over planned busy time), and setup time is a separate element from production time. Our reading of these formulas: a changeover inside planned busy time lowers availability.
Do not move changeovers into planned downtime to lift the OEE figure. Our IRIS article on why OEE is not enough lists "Changeovers or short stops are reclassified as planned time" as one way the number stops meaning anything. Report changeover minutes as their own loss next to live OEE.
What DBR77 IIoT gives for changeover measurement, and where it stops
DBR77 IIoT records the changeover state at the machine together with the machine's own stop and cycle data. Product pairs need order data from IRIS MES or another system.
| What you need | What DBR77 IIoT gives | Where it stops |
|---|---|---|
| Start and end of each changeover | Status Deck: the operator sets running, break, changeover or breakdown in about two seconds, with no PLC and no change to the machine. The operator app shows a machine in setup and how long the current stop has lasted | Operator input; automatic changeover detection is not part of it |
| Stop time and cycle counts | DataHub reads a PLC or a Modbus or RS-485 meter, or uses a stack light tap, motor current or a cycle sensor; it keeps counting when the link drops | Counts, not a first-good-part judgement |
| Changeovers per machine and shift | Stops and reasons per machine and per shift from the Status Deck; machine state on a shift timeline and OEE with availability, performance and quality (machine monitoring) | No ready-made report by product pair or crew |
| Product, order and run-up scrap | Current and next work order, and scrap reported against the order, in the operator view for plants that also use the IRIS MES and QMS modules | Needs the IRIS modules or order data from another system |
| New settings for the next product | Not done: DBR77 IIoT only reads machine data and does not write settings to the PLC | Recipes and settings stay with the machine and its controls |
With DataHub, "the stop time comes from the machine and the reason from the operator", so each changeover record has a measured length and a reason.

Operator app in the animation on the product page: after a stop, the operator picks the reason at the machine (illustrative animation, DBR77).
It fits plants with old and new machines, many without a setup signal, that want every changeover recorded from one operator input plus the machine's stops and counts. It does not fit when you need changeovers detected with no operator input at all, a ready-made SMED task timer, or settings and recipes sent to the machine. A pilot starts on 1 to 3 workstations or one line and ends with a report and a recommendation for scaling.
FAQ
When does changeover time start and stop?
It starts with the last good part of the old run and stops with the first good part of the new run at normal rate. That span holds three phases: run-down, set-up and run-up. A stopwatch from machine stop to machine start covers only the set-up.
Is changeover time the same as setup time?
In lean usage, yes: LEI notes a changeover is "also called a setup". In the ISO 22400 time model as the OPC UA specifications apply it, setup time (AUST) covers only the time in setup mode, and good parts made in that mode count as production time. An MES that reports setup time this way can show less than your changeover time.
Can machine data measure internal and external setup?
It measures internal setup and run-up directly. External work happens while the machine still runs, so time it once in an observation study and keep it on a checklist; the data then shows whether it has moved back inside the stop.
Does changeover time count against OEE?
Yes. The stopped part is an availability loss and scrap during run-up is a quality loss, and slow run-up cycles also lower performance. Moving changeovers into planned downtime makes OEE look better while the minutes stay lost.
How do you measure changeover on a machine without a PLC?
Use a cycle sensor, a stack light tap or motor current for the stops and counts, and let the operator mark the changeover state at the machine. The machine signal gives the length of the stop, and the operator's input says it was a changeover.
Conclusion
Start this week on one machine. Pick the one with the most changeovers, write the start-and-end rule on one page, and for one week have the operator mark every changeover start and end at the machine while the machine supplies stops and counts. At the end of the week, list each changeover with its product pair, internal time and run-up, and note which pair looks worst. After four weeks of records, the worst pair is your first SMED event.
Measure every changeover on one line
A pilot on 1 to 3 workstations or one line, with the changeover state at each machine and stops and counts from the machine, ends with a report and a recommendation. Tell us which machine changes over most.
Sources
- Lean Enterprise Institute, Lean Lexicon: Changeover, 2020
- Lean Enterprise Institute, Lean Lexicon: Single Minute Exchange of Die (SMED), undated (after Shingo, 1985)
- Christoph Roser, AllAboutLean.com, The Phases of a Changeover, 2017
- Mileham, Culley, Owen, Newnes, Giess, Bramley (University of Bath), The impact of run-up in ensuring rapid changeover, CIRP Annals 53(1), 2004
- OPC Foundation and VDMA, OPC 40001-1 OPC UA for Machinery, 13.2 Operation mode and Annex C.2, ISO 22400 time elements, 2026
- OPC Foundation and VDMA, OPC 40501-1 OPC UA for Machine Tools, Annex C.2 KPI calculation, 2026
- OPC Foundation and OMAC, OPC 30050 OPC UA for PackML, 2026
- OEE.com (Vorne), The Six Big Losses, 2026
- Engelmann, Schmitt, Miller, Bräutigam, Schmitt, Advances in Machine Learning Detecting Changeover Processes in Cyber Physical Production Systems, Journal of Manufacturing and Materials Processing 4(4), 2020
- NIST Manufacturing Extension Partnership, Success Story: Improvement Effort Reduces Changeover Time, 2018